Wire Rod Mill Revamping

  • Fast-Track Revamping
Service
Detail Design and Civil works
Location
Cargnacco (UD), Italy
Client
ACCIAIERIE BERTOLI SAFAU SPA
Year
2017
Shut-down period
30 Calendar days
Technological supplier
Danieli Spa

Ferretti Construction carried out the detailed civil design and civil works for the revamping of a wire rod mill at the Acciaierie Bertoli Safau SpA plant in Cargnacco (UD), applying its proprietary Fast-Track Revamping methodology.

The project, developed in collaboration with technology supplier Danieli SpA, was completed within a 30-day production shutdown window.
The intervention required efficient management of critical phases and precise coordination with mechanical and process disciplines, ensuring full integration with the existing plant layout and strict adherence to project timelines.