Twin Ladle Furnace Installation

  • Mechanical and piping installation
Service
Mechanical and Piping Installation
Location
Italy
Year
2019
Technological supplier
SMS Group Spa

Ferretti Construction carried out the mechanical installation, piping, and steel structure assembly for a new Twin Ladle Furnace at an industrial facility in Italy.

The project, executed between December 2018 and February 2019, involved:

  • 152 tons of mechanical equipment installation
  • 15 tons of piping and supports
  • 143 tons of steel structures

All activities were performed with high standards of precision and safety, ensuring the seamless integration of the new system into the existing production layout, without interference to ongoing operations.

Timeline:
December 2018 – February 2019