Project
Shear Foundation Revamping
Service
DETAIL DESIGN AND CIVIL WORKS ON A FAST-TRACK REVAMPING BASISLocation
Duisburg, GermanyYear
2024Shut-down period
20 calendar daysTechnological supplier
PRIMETALS TECHNOLOGIES AUSTRIAFerretti Construction carried out the detailed design and civil works for the revamping of the shear foundation at a steelmaking facility in Duisburg, Germany, applying its proprietary Fast-Track Revamping methodology.
The project was completed during a 20-calendar-day production shutdown, finishing 2 days ahead of schedule. The civil works included demolition, excavation, diamond cutting and core drilling, as well as the positioning and casting of the pre-assembled foundation blocks.