Project

Shear Foundation Revamping

  • Fast-Track Revamping
Service
DETAIL DESIGN AND CIVIL WORKS ON A FAST-TRACK REVAMPING BASIS
Location
Duisburg, Germany
Year
2024
Shut-down period
20 calendar days
Technological supplier
PRIMETALS TECHNOLOGIES AUSTRIA

Ferretti Construction carried out the detailed design and civil works for the revamping of the shear foundation at a steelmaking facility in Duisburg, Germany, applying its proprietary Fast-Track Revamping methodology.

The project was completed during a 20-calendar-day production shutdown, finishing 2 days ahead of schedule. The civil works included demolition, excavation, diamond cutting and core drilling, as well as the positioning and casting of the pre-assembled foundation blocks.