Project
Rolling Mill Stands #1 and #2 Installation
Service
Mechanical and Piping InstallationLocation
Lonato (BS), ItalyYear
August, 2018Ferretti Construction carried out mechanical assembly and piping works for the installation of rolling mill stands no.1 and no.2 at the Lonato (BS) plant in Italy.
The intervention, scale pit’s hydrocyclone piping replacement and replacement of the old flushing channel and completed in August 2018, required high-precision alignment and assembly activities to ensure proper integration with the existing production line and compliance with the commissioning schedule.
Location: Lonato (BS), Italy
Schedule: August 2018


