Project

Revamping of Rolling Mill & New Billet Welding Machine

  • Fast-Track Revamping
  • Project management and supervision
Service
Detail Design & Project Management
Location
Abu Dhabi, UAE
Client
UNION IRON & STEEL COMPANY
Year
April, 15th 2018 - May, 07th 2018
Shut-down period
23 Calendar days
Technological supplier
Primetals Technologies Italy Srl and ATS Spa

Ferretti Construction carried out the revamping of the rolling mill and the setup for the new billet welding machine at the Union Iron & Steel Company plant in Abu Dhabi (UAE).

The scope included detail design and project management, overseeing on-site operations and managing technical interfaces with technological suppliers Primetals Technologies Italy Srl and ATS Spa.

All works were completed during a 23 calendar days, from April 15th to May 7th, 2018, in full compliance with the plant’s tight production schedule.