Project
Revamping of the MCC1 Continuous Casting Steam Chamber
Service
Civil detail design and civil worksLocation
UdineYear
2025Technological supplier
DanieliFerretti Construction carried out the detailed design and civil works for the revamping of the MCC1 continuous casting steam chamber at a steel plant in Udine, Italy.
The civil works included diamond disk and wire cutting, core drilling, operations in confined spaces, and the use of a suction excavator to ensure safety during excavation in sensitive areas. The project was completed in Summer 2025, with a three-week pre-shutdown phase and a production shutdown of just 3 calendar days, finished one day ahead of schedule.