Ferretti Construction was responsible for the detailed design and execution of the civil works for the construction of new foundations for a slitting line at a production facility in Reggio Emilia, Italy.

The project required deep excavation down to -8,00 m, with a finished pit depth of -7,00 m, below the groundwater table located at -2,50 m. These conditions demanded high technical standards for water management and structural stability.

Construction period:
May – August 2024