October 2022 – January 2023Technological supplier
Danieli SpaFerretti Construction executed the installation of mechanical equipment for the new outlet of a bar mill at the Texas facility, USA.
The project involved the positioning and assembly of equipment totaling 1,201 tons, with careful activity management to ensure full plant integration.
Timeline:
On-site presence: October 2022 – January 2023