Project

Fume Treatment Plant Installation

  • Mechanical and piping installation
Service
Mechanical, Piping and Steel Structures Installation
Location
Dürrenäsch, Switzerland
Year
2021
Technological supplier
AWS Corporation Srl

Ferretti Construction carried out the mechanical, piping and steel structure installation for a new fume treatment plant in Switzerland.

The project was executed in two operational phases:
Phase 1: November – December 2021
Phase 2: December 2021 – February 2022

Fume treatment systems are crucial in industrial processes to reduce environmental impact and comply with regulations. This project reinforces Ferretti Construction’s expertise in the execution of complex environmental installations.