EAF # 1 – Forced Draught Cooler Installation
Service
Mechanical and Welding Works. Welding Type: FW (=Fillet-Weld); BW (=Butt-Weld)Location
ItalyYear
2018Ferretti Construction carried out mechanical assembly and piping works for the installation of a Forced Draught Cooler system connected to Electric Arc Furnace #1 at an industrial facility in Italy.
The project, completed in 2018, included FW (fillet-weld) and BW (butt-weld) welding types, performed to high quality standards to ensure system integrity under thermal and mechanical stress. Activities were coordinated with the plant’s ongoing operations.
Year of execution: 2018