CTL Line Revamping

  • Fast-Track Revamping
  • Mechanical and piping installation
Service
DETAIL DESIGN, CIVIL WORKS ON A FAST-TRACK REVAMPING BASIS, MECHANICAL DISASSEMBLY, MECHNAICAL & PIPING INSTALLATION
Location
Brescia
Year
2025
Shut-down period
26 calendar days
Technological supplier
F.I.M.I. Fabbrica Impianti Macchine Industriali Spa

Ferretti Construction carried out the civil works and installation activities for the revamping of a CTL (Cut-to-Length) line at the SSAB production plant in Brescia, in partnership with the technological supplier FIMI Group.

The project included:
• Dismantling of the existing machines, completed in just 3 days
• Fast-track engineering, developed in-house to meet the shutdown constraints
• Civil works completed in 5 days thanks to the use of pre-assembled foundation blocks
• Mechanical, piping and steel structures installation completed in 18 days

Schedule
Site presence: 15 July – 30 August 2025
Shutdown duration: 26 calendar days