Project
CTL Line Revamping
Service
DETAIL DESIGN, CIVIL WORKS ON A FAST-TRACK REVAMPING BASIS, MECHANICAL DISASSEMBLY, MECHNAICAL & PIPING INSTALLATIONLocation
BresciaYear
2025Shut-down period
26 calendar daysTechnological supplier
F.I.M.I. Fabbrica Impianti Macchine Industriali SpaFerretti Construction carried out the civil works and installation activities for the revamping of a CTL (Cut-to-Length) line at the SSAB production plant in Brescia, in partnership with the technological supplier FIMI Group.
The project included:
• Dismantling of the existing machines, completed in just 3 days
• Fast-track engineering, developed in-house to meet the shutdown constraints
• Civil works completed in 5 days thanks to the use of pre-assembled foundation blocks
• Mechanical, piping and steel structures installation completed in 18 days
Schedule
Site presence: 15 July – 30 August 2025
Shutdown duration: 26 calendar days



