Project

CTL (Cutting to Length) Line Revamping

  • Mechanical and piping installation
Service
MECHANICAL, PIPING AND STEEL STRUCTURES INSTALLATION
Location
KREFELD, GERMANY
Year
2025
Shut-down period
20 calendar days
Technological supplier
FIMI GROUP

Ferretti Construction supported FIMI Group in the revamping activities of a cut-to-length line at the Thyssenkrupp plant in Krefeld, as part of a project commissioned by Thyssenkrupp Stahlkontor.

Ferretti’s scope included the dismantling of the existing packaging line and the installation of the new packaging line. The supply of the machinery, designed and manufactured by FIMI Group, required integrated planning and coordinated execution within a tight schedule.

The main activities included:

  • Dismantling and installation of 50 tons of shear mechanical equipment
  • Dismantling and installation of 60 tons of packaging line mechanical equipment

The project was completed during a scheduled 20-day shutdown, ensuring full coordination with the plant’s production requirements.

Schedule
On-site presence: 1 – 20 December 2025

Gallery