Project
Continuous Caster Machine Foundations Revamping
Service
Civil Detail Design and Civil works on a Fast-Track Revamping basisLocation
ItalyYear
2021Shut-down period
10 Calendar daysTechnological supplier
SMS GROUP GmbH; INDUGA GmbH & Co. KGFerretti Construction performed the civil detail engineering and civil works for the revamping of continuous caster machine foundations in Italy, adopting a Fast-Track Revamping approach.
The project, carried out in 2021 in collaboration with technological suppliers SMS Group GmbH and Induga GmbH & Co. KG, was completed within a very tight 10 calendar days. The intervention required high execution efficiency and precise coordination of design and construction phases to ensure immediate plant restart.