Project

Complete Revamping of Furnace No.2

  • Fast-Track Revamping
Service
Detail Design and Civil works on a Fast-Track Revamping basis
Location
Verona, Italy
Client
VETRERIE RIUNITE SPA
Year
2017
Shut-down period
8 Calendar days
Technological supplier
Stara Glass (Hydra Group)

Ferretti Construction carried out the detailed civil design and execution of civil works for the complete revamping of Furnace No.2 at the Vetrerie Riunite SpA plant in Verona, applying its proprietary Fast-Track Revamping methodology.

The project, completed in 2017 in collaboration with technology supplier Stara Glass (Hydra Group), was delivered within a tight 8-day production shutdown window. The intervention required a high level of operational coordination and careful planning of critical phases, ensuring full compliance with the schedule and seamless integration with the existing plant infrastructure.