Project
Compact Cold Mill Installation
Service
Mechanical and Piping InstallationLocation
ItalyYear
2021Shut-down period
20th December 2021 - 3rd January 2022Technological supplier
SMS Group SpaFerretti Construction performed the mechanical and piping installation for a new Compact Cold Mill in Italy.
The operation, carried out between December 20th, 2021 and January 3rd, 2022, required careful planning and efficient management to meet deadlines during the Christmas holiday period.
Schedule:
December 20th, 2021 – January 3rd, 2022