Project
Billet Welding Machine Revamping
Service
Detail Design and Civil Works on a Fast-Track Revamping basisLocation
GermanyYear
December, 27th 2019 - January, 09th 2020 Shut-down period
13 Calendar days (Technological supplier
Danieli SpaFerretti Construction carried out the revamping of the foundations for a billet welding machine at an industrial facility in Germany, applying its integrated Fast-Track Revamping approach to ensure rapid execution and uninterrupted production.
The site activities took place over a period of two months, from November 20, 2019, to January 20, 2020, including a 13-day production shutdown during which the main structural works were completed 5 days ahead of the contractual schedule.
Timeline:
Site duration: November 20, 2019 – January 20, 2020
Production shutdown: 13 calendar days (completed 5 days ahed of schedule)
Technology supplier: Danieli SpA