Project
New Billet Heating System – Rolling Mill
Service
Civil Detail Design and Civil WorksLocation
ItalyYear
June - August 2021Technological supplier
CEA GroupFerretti Construction carried out the detailed civil design and construction works for a new billet reheating system at an industrial site in Italy.
The three-month project, completed between June and August 2021, included delicate cutting and controlled demolition activities, performed using diamond saw technology to ensure maximum precision, safety, and minimal impact on existing structures. The scope also involved the construction of a new electrical cabin to support the system’s operations.
The entire project was managed with meticulous planning and strict quality control, ensuring compliance with the scheduled timeline and technical requirements.
Schedule:
June – August 2021 (3 months)